November 2019 – News Letter

Preamble

I’d planned to have something out in October, a respectable three months on from the previous issue, but life has an irritating habit of getting in the way of things. As Edmund Blackadder so eloquently put it – “The path of my life is strewn with cowpats from the Devil’s own Satanic herd”. Be assured, however, that I’ve swept up and what follows is wholly fragrant ….

Around and About the Club

Big things have been happening out on the grass of late as work has progressed steadily with building the new Carriage Shed for the raised-track riding trucks. Many cubic metres of soil have been excavated to prepare the ground for the floor-slab (6m long by 2m wide by 10cm deep) which sits several centimetres below the surrounding ground level. Four courses of blockwork are raised on this to roof-eaves level. A door-frame and sill have been fabricated in steel which occupy the full width of the track-ward end. Provision is made in the floor to bring in mains electricity.

Whilst the ground works for the carriage shed were underway, the area in front of the locomotive shed was also prepared to accommodate the new dual-gauge traverser and the slab for this was poured at the same time.

Work also continues with improvements to the track signalling and point control systems. Receiving attention now are the points between the station loop and main line so that these cannot be operated whilst a train is in transit. Additional train-detectors have been installed in the track and associated cables laid-in back to the Signal Box where a new cabinet houses the extra circuitry required.

Creosote Day, Saturday 7th September, witnessed a good turnout of willing helpers to get this annual maintenance job done. Both ground-level and raised tracks were thoroughly treated using a combination of spray-guns and brushes.

If you’ve visited the TSMEE website recently, you’ll have noticed a quite radical change in appearance and content. John Rowley has taken over the job of webmaster and is keen to stress that it is, presently, very much “work in progress”. User feedback and constructive comments are welcomed.

Events …

Open Weekend 27/28th July

This annual two-day event was not blessed with particularly good weather. It rained on-and-off on the Saturday and Sunday was dry but overcast. Nevertheless, there was a respectable turnout of both TSMEE members and visitors, the latter hailing from as far afield as Scotland, Cumbria, York and Leeds.

Visiting locomotives were :– in 3-1/2” gauge  BR “Britannia” 4-6-2, Great Central O4 2-8-0, Freelance 4-8-2 – in 5” gauge  “Chub” 0-4-0 Tank, BR Standard 4 2-6-4 Tank, NER Q6 0-8-0, NER B2 4-6-0 – and in 7-1/4” gauge  GWR 14XX 0-4-2 Tank .

Saturday lunch was Fish ‘n Chips and on Sunday our Catering Stalwarts laid on their usual splendid buffet.

Trip down the Tyne 31st August 2019

Six members joined our party on the “Fortuna” for a cruise down to Tynemouth from the Quayside in Newcastle. The weather was reasonable, even allowing for the blustery wind, and we all enjoyed the trip.

There is a full and very informative commentary on the way to Tynemouth. I have made the trip a couple of times over the years and I am amazed by the way that Tyneside industrial heritage has disappeared in a comparatively short time. It used to be the remains of ship yards, dry docks and associated industries all the way to Tynemouth. Now much of the bank-side is wooded and under modern housing. It all looks very different.

The remaining working areas are impressive and Tyne Dock is massive. The Fish Quay and Tynemouth with the Harbour Lights, like much else of the riverside, are becoming tourist attractions. That’s progress, so we all went to the bar and drank to the past.   Malcolm Phillips

Trip to see the G5 at Shildon and the P2 under construction at Darlington, 7th October 2019.

Another enjoyable day out, perhaps more related to model engineering. Volunteers at both sites were very helpful and thanks are due to Phil Work who kindly arranged tea and biscuits at Shildon.

The G5 is not quite an engine yet, but most of the parts are ready to go together. The frames, boiler, cab and plate-work just need finishing touches. The bogie for the 0-4-4 and one set of driving wheels have been finished but the crank axle has yet to arrive, as manufacture of parts and machining is all done outside. The group has been working to original plans and has had to make many patterns, some of which are placed beside the finished castings.

From Shildon we proceeded to Darlington. The P2, to be named “Prince of Wales”, is a truly impressive machine. Like the G5 it has yet to go onto its wheels, all of which have had their tyres polished to a mirror finish.  Cab and smokebox are on the frames and the boiler cladding is set up on frames beside the locomotive as the boiler is yet to come from Meiningen.

We were told about some of the technical problems – the wheel flanges have been computer designed to ease passage round curves on Heritage Railways and steam distribution will be by poppet valves.

The original Gresley design was not too successful so the designers have used the designs evolved in America after the war which were better. Boiler design has been modified by experience with Tornado and their boilers are interchangeable.

I do not know what will become of the polished wheels – one of the volunteers told me that the painters were upset because on its first trip to York of thirty miles, their beautiful paint finish was spoiled by excess grease and oil coming out of the axle boxes!

The NELPG shops were closed so we completed the trip with a visit to the Head of Steam Museum across the way from the Hopetown works. This is a nice museum with exhibits of Stockton and Darlington and NER origin. Hackworth’s “Derwent” and “Locomotion” are well displayed and there are some interesting small exhibits.   Malcolm Phillips

For your diary …

Public Running Day – Santa Special – Sunday 1st December

Christmas Tea – Sunday 22nd December

Something a bit different now – Gordon Bullard has very kindly submitted the following rather interesting article…

An Automatic Cylinder Drain-cock

Back in the 1980’s over a pie and a pint in a local hostelry, a friend and I were discussing the pros and cons of cylinder drain cocks and associated linkage to the cab of a miniature steam locomotive. 

The locomotive he was building had two sets of Stephenson’s valve gear and an axle pump between the frames, together with lubricator linkage which left little room for direct drain- cock rodding.   We discussed the possibility of automatic drain cocks and I suggested that a small inverted safety valve type of arrangement might be possible.

A set of small valves was made and fitted, each consisting of a stainless ball which was held on its seat by a small bronze spring.  The valves performed well but they looked like upside-down safety valves, which is, of course, exactly what they were.

Clearly, a horizontal arrangement was required which would be more prototypical of full sized practice. So, another set of valves was made in a tee configuration with basically the same internal arrangement but in a horizontal orientation.

These valves worked reasonably well. They certainly cleared the cylinder condensate very efficiently but for some reason when the locomotive was running slight puffs of steam were occasionally noticeable. 

Closer observation showed that one of the valves seemed to be working well with no visible leakage whilst the loco was running.  With the expectation that the poor sealing of the three sub standard valves was probable due to poor workmanship on my part,  all of the valves were disassembled for examination.

I was amazed to find that I had forgotten to put a spring in the valve that worked perfectly.  The valves were quickly reassembled without springs and found to all work perfectly.  Since then I have fitted this type of valve onto three of my locomotives with no failures.  The last loco was to LBSC’s “Maisie” design and has run on the club track on numerous occasions.  The attached drawing shows the design of the valve which is made of bar material with a silver-soldered joint.

 It took a while to work out how the valve worked without a spring.  When the locomotive is stationary any condensation in the cylinder drains down into the valve where the ball is resting on the bottom of the chamber so any water can drain away via the front hole. 

When the regulator is opened a combination of condensate and steam enters the valve where the ball is unable to seat properly due to the turbulence in the chamber.  A combination of water and steam exits the valve due to this turbulence until all of the water is displaced, which leaves the chamber full of steam which in turn forces the ball onto its seat.  It’s as simple as that.

You may well ask what the reduced diameter on the rear of the valve is for.  It is purely there to improve the fitting visually, disguising the fact that it is just a piece of simple bar material.  For members who follow full size practice and require drain piping to the locomotive’s buffer beam,  the front of the valve seat could have a small ME thread machined onto it to take a nut, nipple and associated pipe.

In conclusion, this simple valve is easy to produce, is fully automatic in operation and requires no linkage to the cab.  It would be easy to say that I had a light bulb type of moment concerning this valve’s conception but in reality it came about more by accident than design.

Drain-cocks fitted to 3-1/2″ “Maisie”

Postamble

As I remarked in the previous issue, a Newsletter requires News, and this one would have been a rather thin affair but for the contributions of Malcolm Phillips and Gordon Bullard. My thanks to them both.

Membership Subscriptions will be due for renewal at the end of the year. The cost remains at £35 Single and £45 Family. Our Treasurer Ian Spencer will take payment in cash or cheques (payable to “TSMEE Ltd”).

K3 2007-13.jpg
The two tender frames erected
K3 2007-14.jpg
The 4200 gallon tender frame close up
K3 2007-15.jpg
And a view from above
K3 2007-16.jpg
The 3500 gallon tender frame. Note the simple design compared with the later type
K3 2007-17.jpg
And a view highlighting the riveted dragbox, a difficult assembly
K3 2007-18.jpg
The loco and tender frames exhibited at Harrogate in 2007
K3 2007-19.jpg
The LNER tender with axleboxes
K3 2008-21.jpg
Two dozen spring hangers part machined
K3 2008-22.jpg
Part machined hangers on the drawing
K3 2008-23.jpg
Spring hangers almost complete
K3 2008-24.jpg
Machining the backs of the hangers
K3 2008-25.jpg
All nearly finished
K3 2008-26.jpg
A Spencer spring block top being machined
K3 2008-27.jpg
Spring blocks in various stages of manufacture
K3 2008-28.jpg
Sets of six blocks in various stages of final hand finishing
K3 2008-29.jpg
Spring plates halfway through bending
K3 2008-30.jpg
The plate roller made for the job
K3 2008-31.jpg
Plates bent, drilled and ends chamfered ready for assembly
K3 2008-32.jpg
A top plate in the jig for soldering the retaining bars in place
K3 2008-33.jpg
The GNR frames with springs in place
K3 2008-34.jpg
The LNER frames ditto and ready for the tank. April 2008
K3 2007-20.jpg
Photo_08-01.jpg
October 2008 Once the tender frames were erected the next step was the tanks. Here is the sole plate for the GN 3500 gallon tender marked out for drilling and cutting out the holes
Photo_08-02.jpg
Now clamped to the milling machine the holes for the blind bushes for the holding down studs have been drilled and a start is being made on the larger cut outs.
Photo_08-03.jpg
All the machining operations done and the angle fitted for the side and end plates and the blind bushes in place.
Photo_08-04.jpg
The side plates have been bent and are standing on the sole plate. The gap at the back is to be filled with a narrow strip with lap straps riveted in place. This is easier than attempting to make the two sides meet in the middle. They can be machined exactly the same and the gap can be accurately measured for the filler plate.
Photo_08-05.jpg
This is one of the internal splashers required because the large diameter wheels foul the sole plate
Photo_08-06.jpg
The sides now in place and fixed with countersunk screws. These are preferable to rivets as riveting, apart from being awkward, causes distortion of the plates.
Photo_08-07.jpg
A side view of the tender showing the screws. The vertical plate inside is a stiffener to strengthen the body as the driver will ride on a seat on the tender.
Photo_08-08.jpg
The tender back showing the filler piece in place
Photo_08-09.jpg
A view with the front plate and top angles now fitted
photo_08-10.jpg
This is the well tank on the milling machine for cutting the opening for the strum box where the filters live and water is drawn off by the locomotive’s injectors. The well is of riveted construction with flanged end plates. Made in two halves it has an external lap strap which is visible when the tender is completed.
Photo_08-11.jpg
These are the vertical stanchions that carry the coal rails round the top of the tender and were bent up and drilled for the rivets on a former.
Photo_08-12.jpg
The top flares have been fitted ready for the coal rails and the coal space plates have been bent up and fitted. The cavities at each side form cupboards
photo_08-13.jpg
Now advancing well the coal rails are in place and all the beading has been fitted and riveted and soldered. The front plate is complete with the cupboard doors and is being checked for fit before being screwed to the angles
photo_08-14.jpg
A view of the tender from the rear without the coal space plating
photo_08-15.jpg
The 4500 gallon tender had gone through a similar process prior the the GN tender, but for some reason I had neglected to take photographs. Here is a front view. The platework is held together with screws at this stage. Although this version of the Group standard tender was welded, the beading was still riveted on and these can clearly be seen.
Photo_08-16.jpg
Rear of the 4500 gallon tender
Photo_08-17.jpg
Side view of the 4500 gallon tender
Photo_08-18.jpg
Boring the holes in the tank top
Photo_08-19.jpg
Top view of the two tenders before final soldering
Photo_08-20.jpg
Front view of both tenders
Photo_08-21.jpg
Rear view of both tenders
Photo_08-22.jpg
Both tenders will be fitted with water pick up apparatus given time. The fixing points are incorporated in the bottom of the tanks and this is the top of the riser pipe. Whilst it is unlikely ever to be used for taking water it serves as an overflow for when the tank is being filled and saves water being sprayed all over when the tank is full
Photo_08-23.jpg
Now that all the main components have been made and fitted together, they were dismantled and cleaned ready for final assembly and soldering. This is the 4500 gallon sole plate.
Photo_08-24.jpg
One side plate erected
Photo_08-25.jpg
And the inside view
Photo_08-26.jpg
Front back and side plates erected ready for soldering showing the internal stiffeners.
Photo_09-01.jpg
The tenders were substantially complete by March 2009 requiring only the fixtures and fittings – brake gear, water valves and the like, so work returned to the locomotives. The horn stays were fabricated next so that the horn gaps could be secured for final machining. Here is a set of frames on the milling machine for this operation.
Photo_09-02.jpg
A close up of the machined horn faces
Photo_09-03.jpg
And now with the horn stays in position
Photo_09-04.jpg
Now the frames were ready for the axleboxes a length of cast gunmetal was milled to size.
photo_09-05.jpg
Here is the short length ready for cutting into individual blocks
Photo_09-06.jpg
Twelve squared blocks ready for machining
Photo_09-07.jpg
Chain drilling the axlebox to create the split bearing
Photo_09-08.jpg
After saw cutting each side the material is broken out using a taper punch
Photo_09-09.jpg
An embryo axlebox
Photo_09-10.jpg
Axleboxes in various stages
Photo_09-11.jpg
After machining the slots the under trays are machined to fit and the box is centered in the four jaw chuck and bored to size
Photo_09-12.jpg
Boring in progress
Photo_09-13.jpg
Milling the axlebox sides
Photo_09-14.jpg
Twelve axleboxes machined all over
Photo_09-15.jpg
An oil tray ready for milling out
Photo_09-16.jpg
And the finished article ready to have the filler and fixing lug fitted
Photo_09-17.jpg
An axlebox front with the oilseal carrier fitted. A plaited wool seal will go into the brass ring to prevent dirt getting in to the bearing
Photo_09-18.jpg
Machining the oil grooves on the horn faces of the axleboxes
Photo_09-19.jpg
Completed oil grooves. The two small pins securing the underkeep and the larger pin for suspending the leaf spring can bee seen
Photo_09-20.jpg
An axlebox ready for final fitting.Next the axles. This was February 2010 a year from stopping work on the tenders

Contact info …

Newsletter Editor – Mike Maguire ~ mike.maguire@btinternet.com

Club Secretary – Linda Nicholls – lindanic@sky.com ~ 01 670 816072

Website – John Rowley – webmaster@tsmee.co.uk ~ 07970 164 967

For your information – a PDF copy of this News Letter can be downloaded here ….