Stage 9 – Cylinders continued

back to build summary ….

Photo 1.JPG
A middle cylinder with most of the top plates in place
Photo 2.JPG
After the final pieces of the exhaust passage tops were fitted a piece of plate was prepared for bending up to make the smokebox saddles, seen here on the milling table after machining the sides and ends
Photo 3.JPG
Here is the set up for bending the plate. Another good reason for having a thick walled smokebox. As can be seen the plate is laid on the top of the vice with the smokebox on top and a steel bar passed through it. The screwed rod goes through the bare at each end and passes through another bar underneath , and by tightening the screwed rods, the plates bend to the radius of the smokebox, so theory has it.
Photo 4.JPG
The bending progresses
Photo 5.JPG
The bending progresses continued
Photo 6.JPG
The bending progresses continued
Photo 7.JPG
The bending progresses continued
Photo 8.JPG
The bending progresses continued
Photo 9.JPG
The bending progresses continued
Photo 10.JPG
The bending progresses continued
Photo 11.JPG
Here the bent plate is seen sat on the frames before it is cut into two pieces
Photo 13.JPG
After cutting the bent plate is attached to the smokebox, now mounted on the rotary table in the milling machine
Photo 15.JPG
The holes for the saddle bolts are drilled using the rotary table to locate them
Photo 16.JPG
Each hole is counterbored before tapping .
Photo 17.JPG
Tapping in progress
17a (All the bolts fitted).JPG
All the bolts fitted
Photo 19.JPG
Whilst the smokebox is mounted on the rotary table, the opportunity was taken to make some of the openings in it. Here the hole for the snifting valve has been drilled and the first stage of the hole for the chimney is in progress
19 (corrected 231019.JPG
Next the boring head is employed to open out the hole to its correct dimension
Photo 20.JPG
Next the boring head is emp1oyed to open out the hole to its correct dimension continued
Photo 21.JPG
Next the boring head is emp1oyed to open out the hole to its correct dimension continued
Photo 22.JPG
During WW2 most LNER loco smokeboxes lost their countersunk rivets round the back at the boiler connection and round the front at the smokebox door ring in favour of roundheads which require less labour, as there is no need for them to be flushed off. By the late fifties many engines had regained the countersunk rivets at the front , but the round head were still used at the back. This applied to 61962 and I decided to put in dummy rivets (the boiler connection being a simplified version more appropriate for the model). This required drilling around 90 1/32" diameter holes through the 9/32" thick steel, and here it is in progress
Photo 23.JPG
This was, much to my surprise accomplished with just one 1/32" drill, seen here in close up
Photo 24.JPG
The large opening over the inside cylinder was also machine during this set up on the rotary table. First a slot was machined right through the saddle plate and the smokebox
Photo 25.JPG
This was then extended to the full width of the opening
Photo 26.JPG
And then extended to the full extent of the opening
Photo 27.JPG
The Final break through
Photo 28.JPG
Next the outside of the saddle was machined to size.
Photo 29.JPG
Other holes for the handrail stanchions and the bake ejector exhaust wer also drilled at this time
Photo 30.JPG
At last the saddle plate could be fitted to the inside cylinder with more temporary 10 BA screws.
Photo 31.JPG
The holes above the exhaust ducts in the side plates were plugged.
Photo 32.JPG
And the little gusset plates made and fitted to the front and back of the saddle.
Photo 33.JPG
The Inside cylinder main steam pipe flange was turned up and carefully fitted as it needs to be vertical.
Photo 34.JPG
After masking the areas that would not benefit from the application of silver solder the cylinder was fluxed ready for what will be the final soldering operation.
Photo 35.JPG
The cylinder is ready for final soldering.
Photo 36.JPG
The cylinder is ready for final soldering continued
Photo 37.JPG
The cylinder is ready for final soldering continued
Photo 38.JPG
Two inside cylinders after soldering.
Photo 39.JPG
The inside cylinder assembly mounted on the rotary table for machining the side flanges. By using the rotary table some certainty can be give to the alignment of the middle cylinder by making finishing cute on the same tool settings each side.
Photo 40.JPG
The initial cuts brought the ends of the exhaust ducts flush with the flanges
Photo 41.JPG
The right hand flange finished
Photo 42.JPG
And the left
Photo 43.JPG
Checking the width of the cylinder with a 6" micrometer.
Photo 44.JPG
With the cylinder rotated 90 degrees the top of the slide bar support could be machine d accurately parallel with the cylinder centre line.
Photo 45.JPG
The outside cylinders were also set up on the rotary table for the slide bar bracket initial facing. The cutter can only reach a part of the face because the machined surface extends under the end of the valve chest.
Photo 46.JPG
The cylinder is then mounted vertically on the milling table to complete the machining of the bracket. The internal corners are unable to be machined and needed finishing using a very sharp chisel and swiss files.
Photo 47.JPG
With the outside cylinders now mounted on an angle plate on the milling table the footplate angle support could be machined.
Photo 48.JPG
And the main steam inlet bored with a bull nose cutter.
Photo 49.JPG
Likewise for the inside cylinder the steam pipe bore is finished and the inlet and exhaust flanges faced off.
Photo 50.JPG
Mounted the other way up the draincock flanges are faced and the holes drilled.
Photo 51.JPG
As the side faces of the middle cylinder were faced with the block parallel to the cylinder there is a triangle under the saddle that needs machining. The cylinder was set up on the milling table with the saddle parallel to the boiler centre line and a ball nosed milling cutter used to finish the flange and put a radius between the saddle and the flange.
Photo 52.JPG
As the side faces of the middle cylinder were faced with the block parallel to the cylinder there is a triangle under the saddle that needs machining. The cylinder was set up on the milling table with the saddle parallel to the boiler centre line and a ball nosed milling cutter used to finish the flange and put a radius between the saddle and the flange.
Photo 53.JPG
Back on to the rotary table now to machine the bottoms of the transverse supports, which because of the inclination of the cylinder are all different. The cylinder set up viewed from the side shows the angles marked on for the machining operation.
Photo 54.JPG
After machining this end view shows the shape of the underside of the cylinder to which the lagging will be attached.
Photo 55.JPG
The next operation reverted to the lathe, with the cylinders mounted on the vertical slide for accurate finishing of the steam chest bores with a between centres boring bar.
Photo 56.JPG
A completed steam chest bore almost ready for the liner.
Photo 57.JPG
A similar method was used for the inside cylinder.
Photo 58.JPG
The valve liners were the next step towards completion of the locos. Twelve lengths of cast iron were prepared and bored for the liners.
Photo 59.JPG
A mandrel had been made that fitted in the 2 Morse taper of the lathe which was also centred at the outer end for support with the back centre. The valve liner blacks were fitted in pairs between spacer blocks for machining.
Photo 60.JPG
All the roughed out blanks were remounted on the mandrel, again in pairs, and and machined to the correct diameter, leaving a flange at one end.
Photo 61.JPG
Mounted in the four jaw chuck the liners were accurately centred with a dti.
Photo 62.JPG
And through bored to the required diameter.
Photo 63.JPG
A chamfer was machined in to both ends to help with getting the ringed valve heads in to the liners. Those on the inner end help to get the heads through from the front to the back valve passages.
Photo 64.JPG
Back to the rotary table and a milling cutter was used to start forming the ports.
Photo 65.JPG
Showing the initial holes all drilled and a 1/16" cutter mounted ready to square off the ports.
Photo 66.JPG
Two liners with the ports almost complete.
Photo 68.JPG
An outside cylinder with a liner entered ready to be pressed home.
Photo 69.JPG
An inside cylinder with a length of screwed rod in place ready to press the liners in.
Photo 70.JPG
Checking to see the liners are all the way home with a 6" micrometer.
Photo 71.JPG
- A view through the valve chest with the liners in place.